IQ Test Labs

Discover your intellectual strengths

practice questions

4/6 Construction workers

 Four workers are able to place fourty tiles in ten minutes. How many workers are needed to place sixty tiles in twenty minutes?

For four workers, the rate of placing tiles is four tiles per minute.

One worker will place twenty tiles in twenty minutes.

Add Comment

* Required information
1000
What is tset spelt backwards?

Comments (4)

Gravatar
New
Trustin mesays...

Four workers are able to place forty tiles in ten minutes; therefore their rate is 4 tiles/min

One worker's rate is 1 tile/min.

In twenty minutes, a worker will place 20 tiles.

If sixty tiles have to be placed in that time, 3 workers will be needed.

Gravatar
New
Mathew Foksays...

This question can be hard if you don't know the strategy.

Gravatar
New
Mathew Foksays...

It is basically, the rate of the rate.

Gravatar
New
Mathew Foksays...

So I came across this in another example, but the answer is a proportion of all rates. 4w/40tiles/10min = x/60tiles/20min. 4w/4 = x/3 x = 3 workers

Gravatar
Regular
vmaxsays...

Thanks for the explanation!

widgets Latest post

Mathematics skills

new_releases Newsletter

Get new questions to hone your IQ!

whatshot In the news

Keeping the beat

drums beat

pie_chart Polls

Quotations